Project and Portfolio Management Practitioners Forum
cancel
Showing results for 
Search instead for 
Did you mean: 

Previous TimeSheet Items On Newly Created TimeSheets

SOLVED
Go to solution
Highlighted
Sevilay
Collector

Previous TimeSheet Items On Newly Created TimeSheets

Hi,

our users don't want to see the tasks which are entered on previous timesheets in the suggested items tab.There are lots of items which makes the list crowded and difficult to track.
How can i remove them ?

Thanks in advance.
2 REPLIES
Sascha Mohr_1
Esteemed Contributor
Solution

Re: Previous TimeSheet Items On Newly Created TimeSheets

Hi, I have never modified the HP supplied rules for that, but you would do so in PP_HOME\conf\quicklist\QuickListMaster.xml and then set there the enabled to N:

work_items_on_last_timesheet
N
core_derivations/workitems_on_last_timesheet.xml


Most likely you will need to restart the nodes.
hth
Sevilay
Collector

Re: Previous TimeSheet Items On Newly Created TimeSheets

I applied the Sacsha's suggestion.
//Add this to "OnDomLoad" event