Hi,

our users don't want to see the tasks which are entered on previous timesheets in the suggested items tab.There are lots of items which makes the list crowded and difficult to track.
How can i remove them ?

Thanks in advance.
2 REPLIES
Sascha Mohr_1
Outstanding Contributor.
Solution

Re: Previous TimeSheet Items On Newly Created TimeSheets

Hi, I have never modified the HP supplied rules for that, but you would do so in PP_HOME\conf\quicklist\QuickListMaster.xml and then set there the enabled to N:

work_items_on_last_timesheet
N
core_derivations/workitems_on_last_timesheet.xml


Most likely you will need to restart the nodes.
hth
Sevilay
Honored Contributor.

Re: Previous TimeSheet Items On Newly Created TimeSheets

I applied the Sacsha's suggestion.