PPM resource load breakdown

Highlighted
AlbertoS
Contributor.

PPM resource load breakdown

The Resource Load Breakdown - Assignment Summary shows for each resource the TotalCapacity /TotalAssignments /AvailableCapacity on a weekly basis and for a predefined period (i.e. current week + 4 weeks). Is possible to customize the period and the granularity (e.g. day basis)? Thanks
2 REPLIES
mcmunnd1
Respected Contributor.

Re: PPM resource load breakdown

I had asked the same question of HP. The short answer is no - they are not customizable. The direction to me was to use the Analyze Assignment Load graphical portlet to change the period and granularity and then export if needed.
Semenov Alexand
Acclaimed Contributor.

Re: PPM resource load breakdown

For this I use analyze assignment load portlet. In setting of this portlet allow periogs:day,week,month,yer,quarter.
This is wery powerful portlet.
Good luck.