Hi All,

 

Our PPM goes down anytime and we find out that Java process gets killed automatically even at the times when here is not high degree of load. Can u suggest what we should do to prevent this further.

 

Thanks

 

1 REPLY
Etienne_Canaud
HPE Expert

Re: PPM goes down

Well, PPM version would help for a start, and the next logical step would be to look at the server logs around the time the node goes down.
When was this PPM server set up? Did anything change in your environment prior to seeing these issues appearing?