PPM - Workbench - Time Period

Hello everyone,

I'm need to change the time period from the Workbench so that The users can see more past dates. Anyone know how you can change? Please send me the steps. 
If you check in Open / TimeManagement / TimeSheets / SearchTimeSheets. Please check the screenshot attached.

Thanks for the help you can give me

 

 

3 REPLIES
Alessandro Baio
Trusted Contributor.

Re: PPM - Workbench - Time Period

Hello,

I'm afraid that option is not on workbench side, you might try looking into server.conf configuration parameters.

The following sound like candidates:

TMG_FUTURE_PERIODS_TO_ALLOW
TMG_PAST_PERIODS_TO_ALLOW
TM_MAX_PREVIOUS_TIME_PERIODS

Best Regards.

Alessandro

maceguo01
Contributor.

Re: PPM - Workbench - Time Period

Thanks Alelssandro for your reply but I can not find any of these parameters within the file server.conf.

Is there another option? 

Thanks! 

Regards!

Alessandro Baio
Trusted Contributor.

Re: PPM - Workbench - Time Period

Hello,

if not explicitly mentioned in server.conf the parameters are defaulted.

According to Installation and Administration guide the following are their default values:

TMG_FUTURE_PERIODS_TO_ALLOW=10
TMG_PAST_PERIODS_TO_ALLOW=10
TM_MAX_PREVIOUS_TIME_PERIODS=4

I would suggest to explicitly add them to server.conf, then run kUpdateHtml.sh and restart the server in order to pickup the new configuration options.

Which PPM version are you on? You might take advantage of the Administration Console web tool to change server parameters without manually editing the server.conf file (see enclosed screenshot) - some changes don't even require server restart.

Best Regards,

Alessandro