I am looking to gather information regarding the integration which needs to be setup between HP PPM and HP SM.The highlevel infrmation which I have is as below.

 

A task from PPMC  work plan is designated as an operational
 change
Work groups are managed in Service Manager
PPM Creates  a Request For Change in service manager from the
 task
Request For Change shows up in the IT Operations group’s work 
queue.

 

 

I still havent got the documents on HP PPM to HP SM integration. If any1 is having the document, please share.

 

Also correct me if I am wrong with the above understanding on integration.

 

Thank you

 

I am Listening..
1 REPLY
mike_se
HPE Expert

Re: PPM - SM Integration.

Hi,

 

The "Solution Integrations Guide" is the one you want on the Manuals Site.

 

Here is the url for the 9.2 Guide.

If on 9.1, can get that version's Guide on the Manuals Site.

 