PPM Integration issue with MSP.

Highlighted
KiranDubbaka
New Member.

PPM Integration issue with MSP.

Hi,

 

We are having HP PPM 9.22 version and currently working on the  Integration of HP PPM with MicroSoft Project (2013). And ,we are taking an Integration mode as "Shared mode" . Where,

 

- Work breakdown information is controlled by Microsoft 

- Actuals tracking information is controlled by PPM 

 

But,  when we try to "Send Workplan to PPM"  the option itself is disabled in MSP. Hence, we are not able to send the Workplan created in MSP to HP PPM.

 

Could you please look into the issue and let us know the root cause?

 

For reference, I am attaching the screenshot of the option showing as disabled?

 

 

Thanks,

Kiran

1 REPLY
Etienne_Canaud
Outstanding Contributor.

Re: PPM Integration issue with MSP.

Hi Kiran,

 

It may be that this mpp file is not properly associated with the PPM Project. Could you share with us the content of the "Project Details" menu item?

 

Maybe someone removed the association to the PPM project; if that's the case, you'll be able to restore it from that menu.

 

Thanks,

Etienne.