We've begun assigning resources in our Work Plans, but our resources are unable to see My Tasks in their portlet.
3 REPLIES
victoria loft
Collector

Re: My Tasks

Tasks assigned to them by their resource manager in the staffing profile.

The reason we are looking into this, is we want the resources to be able to update their tasks with % complete at the task level.
Erik Cole
Honored Contributor

Re: My Tasks

My Tasks requires the user to have TM license and View Projects, Update Tasks, or Edit Projects access grant.

Also, check your project settings and the preferences for the My Tasks portlet to see what criteria it is using. Some of your tasks may be getting filtered out based on date, status, etc.

Project work plan must also be status "Active".
victoria loft
Collector

Re: My Tasks

Thank you - that fixed it.