Project and Portfolio Management Practitioners Forum
cancel

MS Project integration with PPMC 7.5 (and future releases)

Highlighted
Lilian Ng
New Member.

MS Project integration with PPMC 7.5 (and future releases)

Hi,
We are working on MS Project integration with PPMC 7.5 (and possibly future releases of PPMC also). Just wondering whether anyone has any feedback on their experiences (good/bad/different) on this topic?
Are there anything we should look out for, or may experience problem with when MS Project is integrated with PPMC?
Thanks!
1 REPLY
Celil
Acclaimed Contributor.

Re: MS Project integration with PPMC 7.5 (and future releases)

Hi Lilian,

I'm a solution architect for 3 years and I didn't use any sync between MSP and PPM. I always suggest my customer that...
1) create your WBS on MSP beacuse it is easier than PPM. Than send it to the PPM.
2) to show their customer or managers you can export PPM Work Plan to MSP.

For sync work perfect, MSP data and PPM data should be perfectly match. Actually it is not work always.

I send you a document in enclose about MSP integration which detailly described.

Celil
Celil

IT Governance Professional
& PPM Solution Architect