Linking PPM Budget with Oracle

Has anyone linked the PPM budget section with Oracle? A user would like to synchronize the PPM Budget actuals along with the Purchase Order # and the Oracle Number. Has anyone done this? Any recommendations?

Please see the attached example.
2 REPLIES
Darshan Bavisi
Occasional Visitor
Solution

Re: Linking PPM Budget with Oracle

Hi Jaylen,

There's no ootb sync available between PPM budget entity and Oracle systems. This requirement will turn into a full-blown integration project to sync PPM and Oracle for financial data. This will require lot of table and column mappings between both the systems, scheduled reports and sqls to transfer data between the systems, configuring capex - opex policies in PPM based on Oracle and tons of other things coming into existence to do this sync between both the systems. Mostly PPM gets affected from configuration, enterprise financial policy setups, etc. point-of-view to do this sync.
Jaylen Smith
Regular Collector

Re: Linking PPM Budget with Oracle

I received the info I was looking for.
//Add this to "OnDomLoad" event