Is there a portlet for this?

We are currently doing some testing in our dev environment and had some questions:
We created a new project and attached a staffing profile and workplan to this project. We assigned a task in the workplan to a resource and we are wondering if there is a portlet that can be added to the resource's personal dashboard so they can view and update the status of that task. We added some new portlets but they all show requests rather than low level tasks from the workplan.
Are we missing something?
3 REPLIES
Semenov Alexand
Acclaimed Contributor.
Solution

Re: Is there a portlet for this?

Hi. This is "My task" portlet.Show name task and project,sched start and finish, %, sched and act effort.
Good luck
Tweed
Trusted Contributor.

Re: Is there a portlet for this?

We were able to located the "My Tasks" portlet. Now we are having problems getting info to show in this portlet. We have done the following:
1) Add a new workplan to the project
2) Assign Resources to the task(s)
3) Made sure the date range and status was "In Process"
(We added a resource out of our staffing profile)

Any ideas why our portlet is still not displaying any information?

Semenov Alexand
Acclaimed Contributor.

Re: Is there a portlet for this?

Hi. In this potlet allow any setting with selecting satatuses, only eith exeptions or reade for ma action.
Also allow task periods.

This portlet workin if your work plan is active. Another task status - it doesn't matter.
Good Luck