Is it possible to view audit history on Budget Changes

Highlighted
Shravan Kathuri
Senior Member

Is it possible to view audit history on Budget Changes

Hi,

We have a requirement where we need to capture the audit history on changes related to budget planned and actual values.Is it possible to view audit history (change history) on Budget changes.

Thanks
Shravan kumar.
2 REPLIES
Darshan Bavisi
Occasional Visitor

Re: Is it possible to view audit history on Budget Changes

Hi Shravan,

I don't think budget change history is stored for the value changes in the budget cells. The only change log maintained is for the status changes in the kcst_budget_txn_hist, unless I am missing something. So similarly, there's no budget baselines available ootb.
Erik Cole
Honored Contributor

Re: Is it possible to view audit history on Budget Changes

Word has it that baselines (snapshots) and auditing for budgets will be in the 8.0 release.