Is it possible for the stakeholder to edit the workplan in 7.1 sp5?

Hi,

We have a requirement where we have to give access to stakeholder to edit the workplan.
Is it possible to achieve this PPM7.1 sp5?

Thanks
Shravan kumar.K
8 REPLIES
Semenov Alexand
Acclaimed Contributor.

Re: Is it possible for the stakeholder to edit the workplan in 7.1 sp5?

Hi Shravan.
It's possible
You need do this:
set in request user access tab custom token:
[PRJ="[REQ.P.KNTA_PROJECT_PLAN]".PROJECT_STAKEHOLDER_USERNAME] .Give to this token rights to edit request and they can edit WP.
Use it as a custom token resolving a username.
Good Luck
Shravan Kathuri
Honored Contributor.

Re: Is it possible for the stakeholder to edit the workplan in 7.1 sp5?

Hi Semenov Alexander,

I have given custom token
[PRJ="[REQ.P.KNTA_PROJECT_PLAN]".PROJECT_STAKEHOLDER_USERNAME] in the request type "user access" tab and added one user as stakeholder in the project participents of the project.But the added stakeholder was not able to edit the workplan.
Can you please tell me why the added user was not able to edit the WP eventhough i have given edit requests option in the user access tab. Is there any additional grants or additional settings are required to achieve this.CUrrently we are using PPM version 7.1 service pack 5.

Thanks
Shravan kumar.K
Shravan Kathuri
Honored Contributor.

Re: Is it possible for the stakeholder to edit the workplan in 7.1 sp5?

And edit check box for this custom token is disabled.Can i use standard token PROJCT_STAKEHOLDER in the user access tab?

thanks
Shravan kumar.k
Erik Cole
Acclaimed Contributor.

Re: Is it possible for the stakeholder to edit the workplan in 7.1 sp5?

They need Edit Projects access grant (and maybe also Update Tasks) and also you need a Project Management license to edit the work plan.
Shravan Kathuri
Honored Contributor.

Re: Is it possible for the stakeholder to edit the workplan in 7.1 sp5?

Hi Erik Cole,

The stakeholder has all the 3 access grants that you have mentioned.But still he unable to edit the workplan.

Thanks
Shravan kumar.K
Erik Cole
Acclaimed Contributor.

Re: Is it possible for the stakeholder to edit the workplan in 7.1 sp5?

Forgot...with "edit projects" grant he will also need to be put in the Project Managers list under Participants, or be put as a summary task owner on some of the work plan tasks.

If you give him "edit all projects" grant, you don't have to do that but he will be able to edit all projects, which you probably don't want.
Semenov Alexand
Acclaimed Contributor.

Re: Is it possible for the stakeholder to edit the workplan in 7.1 sp5?

Shravan,Good Day.
I test my system (7.5 sp3) but stakeholders can't edit work plan only view.
Sorry
Shravan Kathuri
Honored Contributor.

Re: Is it possible for the stakeholder to edit the workplan in 7.1 sp5?

Hi,

We are not supposed to give "Edit All Projects" grants.Can anyone tell me any alternative solution to have stakeholder edit access to Workplan? It is urgent requirement.

Thanks
Shravan kumar.