Project and Portfolio Management Practitioners Forum
cancel

Integration between Oracle ERP with PPM8.0

Highlighted
Yadav_1
Contributor.

Integration between Oracle ERP with PPM8.0

Hi,

Is there any way to Integrate PPM8.0 with Oracle ERP? Integration requirement is just to import the Project cost from ERP.

Appreciate any response.


Regards,
Radha
2 REPLIES
Sascha Mohr
Acclaimed Contributor.

Re: Integration between Oracle ERP with PPM8.0

Hello Radha,
we are dealing with a similar situation. In our case it is SAP ERP though, what data do you plan to transfer? Actual cost?
regards
Sascha
Yadav_1
Contributor.

Re: Integration between Oracle ERP with PPM8.0

Hi Sacha,

We are using the Time Management for capturing the Labour Cost. We would like to get the non labour cost from ERP to PPM.

Regards,
Radha