I have finished the installation of PPM v7.5 successfully, but I can see the preconfigured life cycle process that the manual present. For example the FPM - Proposal workflow, PFM - Project Workflow, PFM - Asset Workflow.

I don't know if I have to configure something to see and work with those workflows.
2 REPLIES
Jorge Avendano
Trusted Contributor.

Re: I have disable the preconfigured life cycle processes

Hi,
I have finished the installation of PPM v7.5 successfully, but I can't see the preconfigured life cycle process that the manual present. For example the FPM - Proposal workflow, PFM - Project Workflow, PFM - Asset Workflow.

I don't know if I have to configure something to see and work with those workflows.

Thank you for any help.
Semenov Alexand
Acclaimed Contributor.

Re: I have disable the preconfigured life cycle processes

Hi,
you need install Best Practics from box.