How to schedule trainings

Highlighted
riznad
Regular Collector

How to schedule trainings

Hi;

I would like to get information about your configuration.

If a resource is sent to a training, the resource capacity will become lower.

 

How do you schedule trainings?

 

Is your human resources (or any other department) creating a free standing staffing profile and request resources from the resourcepools?

 

or any thig else?

could you

Regards

3 REPLIES
penoles
Regular Collector

Re: How to schedule trainings

let human resources (or any other department) creating a free standing staffing profile and request resources from the resourcepools is a good idea that I haven't think before

riznad
Regular Collector

Re: How to schedule trainings

is there any other application?

practice?

Celil
Esteemed Contributor

Re: How to schedule trainings

Hi riznad,

 

Miscellaneous items like education, vacation etc can be entered/planning from resource calender as non-working day by their resource managers. This allocation reduce resource capacity. Public holidays must be entered main PPM calender. So the resources' calenders can inherit these as non-working day.

 

Another way like your solution, create a project which manage by HR. This project can be a yearly education plan for an education or every single education can be a project. Resource load should be come from work plan. Other items can be still planning from resource calender like vacations.

 

 

PS: Please keep alive our forum via KUDOS the professionals.