How to close a project

How can we mark a project as closed once it is completed and all the activities are marked as done.
2 REPLIES
Sascha Mohr
Esteemed Contributor

Re: How to close a project

Hello Animesh,
you should do that using the project's workflow (the one the project details request uses).
The workflow steps have to be completed manually (unlike the status of the workplan, that changes when all the tasks and milestones are complete). If you like you can have an execution step in your project workflow that sets the status of the workplan though.
Regards
Sascha