Hi,

We have requirement where we need to add custom task user data fields to work plan template.
We believe we cannot add any of the new fields other than below standard fields.

Scheduled Duration
Scheduled Effort
Predecessors
Resources
Role
Activity


One way we were thinking is we can create one temporary project, update all the tasks along with data for those custom user data fields, and then convert that project to work plan template. But when we convert this temporary project to work plan template, we observed that data for those user data fields are not appearing.

Can anyone please help on whether we can add custom task user data fields to work plan template.

 

Best Regards,

Shravan