How could I create a custom workplan baseline

Highlighted
jerome.vovard
Regular Collector

How could I create a custom workplan baseline

Hi,
I want to create a custom baseline containing some tasks of the active workplan and some tasks of the previous workplan baseline.
The OOTB command to create a baseline is ksc_create_baseline. I would want to see the SQL queries used by this command. Or i would want to see how to create a baseline workplan. I already have the SQL code to create a new task.
Thanks for your help,