How can I force a complete rollup?

Highlighted
Sebas Prieto
Occasional Advisor

How can I force a complete rollup?

I need to rollup actuals from time sheets to tasks in projects. But not entering in every time sheet.

Any idea?
1 REPLY
SID_24
Super Collector

Re: How can I force a complete rollup?

Hi

Go to 'Project setting'--> Cost and Effort.
Enable 'Use Time Management to track actuals against this project'. Add task from project to time sheet. Enter % complet and time.