Hi,
Is it possible to update a field everyday automatically without any field change. We are using V6.0, so please help us.
eg:field A should display the diffrence in days between the request created from date to current date.
Since we cant use any field change rules is it possible do diplay the value?

Regards,
Rajesh
2 REPLIES
Mahen M
Acclaimed Contributor.

Re: Help required ro update a field automatically everyday

The Apply on page load is not available in PPM V6.0

Running update PL/SQL Procedure Report every night is an option.

Regards,
Mahendran M
Rashraj
Respected Contributor.

Re: Help required ro update a field automatically everyday

Thanks Mahen