For disable users, how to make them enable in HP-PPM 7.1?

Highlighted
Sushil Kumar Pr
Occasional Advisor

For disable users, how to make them enable in HP-PPM 7.1?

Hi,

We are using HP-PPM 7.1 (SP5). A user has been disabled, we are trying to enable it by specifying the End Date (in workbench-->Sys Admin-->Users) which is greater than SYSDATE. The user still showing in disable state and can’t able to login into the instance.

Any shed on this will be highly appreciated.

Thanks in advance.

Regards,
Sushil
1 REPLY
Semenov Alexand
Esteemed Contributor

Re: For disable users, how to make them enable in HP-PPM 7.1?

Hi Sushil.
You just need delete "End Date" and save changes.