Hello! 

  

We have an issue with project's financial summary. The point is that for every cost line (and for every time period) we need to enter and store 4 different parameters (sums) instead of "Forecast" and "Actual " only. 

  

I wonder if anybody has encountered such task and appropriate developmant maybe?

 

Thanks.

1 REPLY
Jason Nichols K
Acclaimed Contributor.

Re: Financial summary. More aspects of costs.

I had a client that had a similar situation.  They ended up using the Financial Data Tables (introduced in 9.12) to capture the other data point they needed.  There is a bit of a manual coordination to make sure you have comparative lines between the FDT and the FS.