Estimated Time to complete

Highlighted
mantisory
Frequent Contributor.

Estimated Time to complete

Hi there,
Does anyone have any ideas on whether it's possible to disallow a time user to enter a percent complete or ETC? We want the user only to be able to enter actuals, not estimated times or percentages - we will have a PM allocate more time per task if necessary.
Regards,
byron
1 REPLY
Sascha Mohr
Acclaimed Contributor.

Re: Estimated Time to complete

Hi.
You can disable ETC in the project settings or the used project type's settings completely. If you have the users enter time in their timesheets on task level they will be able to enter a percentage of completion, they even have to do so. You could switch the project's time sheet settings to entering time on a higher level (summary task, project level).
Still the assigned resources can set the percentage completed in the respective tasks of course.