Enabling TIme management for Proposals - Why staffing profile is not enabled

Highlighted
sangliraja
Respected Contributor.

Enabling TIme management for Proposals - Why staffing profile is not enabled

Hi,

 

I am in PPM 9.31. I was trying to enable time management for proposal request. In the resource tab in workbench , i can enable time tracking for proposal. But the option to allow resources in the staffing profile is given only for assets. I need this option for proposals as well because staffing profiles are added at proposal stage.

 

I create a support request to HP and got response that it is how the system is designed and asked me to create a ER. As most of us Know ER usually will be onhold and no resolution time. I would like to know if anyone found a workaround to make proposal requests available for users in staffing profile to enter time against.

 

Thanks

Sangiliraja.P