EV graphs not appearing for long running project

Highlighted
pradeep k.r.
Super Collector

EV graphs not appearing for long running project

While trying to generate EV graphs for "Netbeans 6.1" project using the analyse cumulative cost metrics data,We get the message saying "there is not enough data to generate the graphs".
The project has been active since june last year.To get EV the project should have had cost and schedule set and baselined.This is correct. Also the CPI/SPI has been set/shown for the past months.

Thanks to advice here.

Thanks,
Pradeep