EV/CPI/SBI Not being Populated For certain Projects

Highlighted
AShameem
Trusted Contributor.

EV/CPI/SBI Not being Populated For certain Projects

Hello,

There are some projects where we do not see CPI,SPI or EV Analysis being calculated. Health Indicator for these projects is also not being calculated. It does not even show the color as green, it is completely NULL.

These projects have Financials enabled and work load category is marked as 'WorkPlan'

I would apreciate if someone could let us know what is missing for some.

Thanks for your help
2 REPLIES
Mahen M
Acclaimed Contributor.

Re: EV/CPI/SBI Not being Populated For certain Projects

I hope you need to see whether there are any Rules disabled.

Regards,
Mahendran M
AShameem
Trusted Contributor.

Re: EV/CPI/SBI Not being Populated For certain Projects

Thanks for your response, can you please let me know what rules are we talking about. The Project Type Settings have been appripriotely done.

Thanks again