Demand states on Resource Gant diagramm

SOLVED
Go to solution
Highlighted
Alexander (Sua)
Regular Collector

Demand states on Resource Gant diagramm

Hello

 

There is possible to track plan and fact dates of demands implementation on Gant Resource diagramm.

There are some demand states on this diagramm: in planning, active, on hold and compelted (see diagramm agenda in attached file)

 

We can't get what to do in order set demand in "On hold" displaying state

 

Could anyone give any idea?

 

Best Regards, Alexander

2 REPLIES
Erik Cole
Honored Contributor
Solution

Re: Demand states on Resource Gant diagramm

Hi,

 

You can't set a leaf task to On Hold directly, but you can set it's parent to On Hold and all the tasks under that will go to On Hold status.