Date field for Portlets in PPMC 7.5 error

Highlighted
Tarun Paul
Respected Contributor.

Date field for Portlets in PPMC 7.5 error

when we type in 12/1/08 it translates it to 12/1/0008.did any one face the same issue and if so what resolution do we have.

Thanks in advance,
T11
2 REPLIES
Shravan Kathuri
Honored Contributor.

Re: Date field for Portlets in PPMC 7.5 error

Hi Tarun,

What is the validation format for that validation.If the date format is "Long",try changing it to some other value.

Thanks
Shravan kumar.K
Tarun Paul
Respected Contributor.

Re: Date field for Portlets in PPMC 7.5 error

Thanks Shravan for the reply , the date format is normal.
Any way raised an SR with HP and they came back as a defect (ITG Defect Request #205939) in PPMC 7.5.

Thanks,
T11