In which table, the cost violation/exceptions are stored?

1 REPLY
dirkf
Acclaimed Contributor.

Re: Cost violation/cost exception table

Hi PPM 914,

 

could you be a bit mor elaborate about which values you are actually looking for?

CPI and SPI values are set to create exceptions and warnings if you exceed them.

These are calculation-triggers for the cost and schedule health for projects, based on certain formulae that are available for you to check upon.

 

I think the most relevant table for your request would be the following:

 

PM_PROJECT_ROLLUP

This table stores project health information which are normally obtained from

rollup calculation for the whole project or work plan.

 

Attaching the guide for your reference.

If this is not the information that you are looking for, please provide details.

 

Best regards,

Dirk

 