Cost Rule and Resource Rate Calculation

We have only two factors Role and Department

My question is

If we have four different rules define on Role and Department.


Role Department Rate

Rule1 Developer Grade1 15
Rule2 Developer 20
Rule3 Grade1 25



what will be cost of resource with fallowing combination as per PPM 8.0



Role Department Rate
Rsc1 Developer Grade1 ?
Rsc2 Developer ?
Rsc3 Grade1 ?

Rsc4 Developer Grade2 ?
Rsc5 Tester Grade1 ?


As per my knowledger goes fallowing are the rates,
Please correct me if I am wrong.

Role Department Rate
Rsc1 Developer Grade1 15
Rsc2 Developer 20
Rsc3 Grade1 25


Rsc4 Developer Grade2 20
Rsc5 Tester Grade1 25


please help me in knowing ppm behaviour