Copy tasks betwen Project Plans

Is it possible to copy set of tasks from one Project plan to another Project plan in Workbench.

I tried Copy/Paste functions and they works only within one Project Plan.

Any ideas?
3 REPLIES
Mahen M
Honored Contributor

Re: Copy tasks betwen Project Plans

I am not sure how to copy a set of a set ot tasks within PPM.

But you can make use of Microsoft Project Plug-in functionality in PPM. I hope in MPP you can import the plan with new tasks. Just a suggestion.

Regards,
Mahendran M
Erik Cole
Honored Contributor

Re: Copy tasks betwen Project Plans

This is possible in 7.5 by using the 'Import Another Work Plan' feature in the target project's work plan.
Theodore Power
Acclaimed Contributor

Re: Copy tasks betwen Project Plans

Alexei,

I do know that I have created a template of the tasks that I wanted to copy, then added the template to the new work plan.