Project and Portfolio Management Practitioners Forum
cancel

Copy tasks betwen Project Plans

Highlighted
Alexei Malinovs
Respected Contributor.

Copy tasks betwen Project Plans

Is it possible to copy set of tasks from one Project plan to another Project plan in Workbench.

I tried Copy/Paste functions and they works only within one Project Plan.

Any ideas?
3 REPLIES
Mahen M
Acclaimed Contributor.

Re: Copy tasks betwen Project Plans

I am not sure how to copy a set of a set ot tasks within PPM.

But you can make use of Microsoft Project Plug-in functionality in PPM. I hope in MPP you can import the plan with new tasks. Just a suggestion.

Regards,
Mahendran M
Erik Cole
Acclaimed Contributor.

Re: Copy tasks betwen Project Plans

This is possible in 7.5 by using the 'Import Another Work Plan' feature in the target project's work plan.
Theodore Power
New Member.

Re: Copy tasks betwen Project Plans

Alexei,

I do know that I have created a template of the tasks that I wanted to copy, then added the template to the new work plan.

Ted