Changing region on a PPM project

Is it possible to change the region of an active project that has registered actual effort and percentages of progress?. And same for an active, in planning or holded project that has no actuals.

If this is possible how to do it and what permissions are needed?

Thanks in advance.
Jon.
6 REPLIES
Mahen M
Acclaimed Contributor.

Re: Changing region on a PPM project

I hope it is not possible unless you write a update Query. But HP doe's not support it.

See whether you have a hidden 'Region' field in the Header area, I hope there will be none like that, but worth to give a try.

Thank you.

Regards,
Mahendran M
Sascha Mohr_1
Outstanding Contributor.
Solution

Re: Changing region on a PPM project

To date there is no way to change the region of an existing project (regardless of the status), that's also what HP said. I think, there is already an enhancement request for that. Maybe you have yourself being added to the list of requesters.
Regards
Sascha
Jonathan Castil
Trusted Contributor.

Re: Changing region on a PPM project

Thanks Sascha / Mahendran.

In fact I put the same question via "support case" but I didn't received a concrete answer yet. I assumed the same as you told me.

Sascha, do you know the ID for the enhancement request?

Jon.
Sascha Mohr_1
Outstanding Contributor.

Re: Changing region on a PPM project

The ER# is 201277.
Jonathan Castil
Trusted Contributor.

Re: Changing region on a PPM project

Thanks again Sasha.

Have a nice day.
Jon.
Jonathan Castil
Trusted Contributor.

Re: Changing region on a PPM project

Actually I confirmed that there's no way to change project regions on PPM.