Cannot save the Start and Finish period in a proposal

Hi,

 

In a proposal, the Expected Start Period Expected Finish Period is October 2011.

And, Required Completion Date: October 3, 2011.

When I save I have no problem.

But, when  I change he Expected Start Period to August 2011, It won't save and gives the following error messge which is nonsense.

"The time range of periods must include at least one period. Please select a finish period that is not before the start period. (KNTA-10984)"

 

Any help is appreciated.

Version:PPM 7.5 SP7

 

Regards

TM

 

1 REPLY
Kerim KILIC
Honored Contributor.
Solution

Re: Cannot save the Start and Finish period in a proposal

hi,

 

please check

support.openview.hp.com/selfsolve/document/KM912127

may be helpful