Project and Portfolio Management Practitioners Forum
cancel
Showing results for 
Search instead for 
Did you mean: 

Cannot Track Time at Project Level

SOLVED
Go to solution
Highlighted
afraschilla
Occasional Contributor

Cannot Track Time at Project Level

Hello all.  My organization typically has tracked time at the task level.  For a variety of reasons, we have been considering switching to tracking at the project level instead.  I was attempting to test this out to see if it would do what we're looking for, however I can't actually seem to figure out how to get it to work.  I created a dummy project and adjusted the project settings as shown in the attachment.  I then went into my timesheet and clicked on add project, however no results were found when I clickec on search.  We have tracking of projects enabled in the workbench.  Is there another step that I am missing?  Thanks so much for any help.

2 REPLIES
Arjun_K
Member
Solution

Re: Cannot Track Time at Project Level

Hi,

 

There could be couple of more more things to it.

 

1. Check if the Project manager has a staffing profile associated to the project and this user is part of it.

2. Check that the user is assigned to the project.

3. Check the status the Project! If the project is still in planning, user may not log time agains it.

 

 

Warm Regards,
Mallikarjun.S
afraschilla
Occasional Contributor

Re: Cannot Track Time at Project Level

Hi, thank you so much for the reply.  

 

The staffing profile is created with user committed to project and the project status is in execution.

//Add this to "OnDomLoad" event