Can we have default ACTUAL Hrs in Timsheet for a resource every week

HI,

Is it possible to have default Actual hrs filled in the timesheet set for a resourec every week such that resource need not to fill ACTUAL hrs in timesheet every day/week.


Thanks,
Phani
2 REPLIES
himanshukumar
Super Collector
Solution

Re: Can we have default ACTUAL Hrs in Timsheet for a resource every week

Phanishwar,

First of all you need to decide what would be the default task and number of hours for each resources. You can capture this information by creating a custom request type which will store task and hour information for each resources. This way you would have the flexibility to change the default task and hours without any complexities. Then a scheduled job can create and update the timesheet for the resources, picking up the information from the requests.

Hope it helps!

Thanks!
Himanshu
Phanishwar
Collector

Re: Can we have default ACTUAL Hrs in Timsheet for a resource every week

Thanks Himanshu!!.I just wanted to confirm that there is no such default fiiling functionality in PPM7.1 or 7.5 as well.