Can't add task to work plan

Highlighted
roxor
Honored Contributor.

Can't add task to work plan

Dear all,

 

I have following issue. I am assigned to task and I am PM in that project. (work plan was imported form MS Project...) When I want to add tasks to my time sheet, I search for the project a no tasks were found.

 

I am PM on similar project with the same settings and I can add its task to time sheet...

 

I have no idea what is wong. Only difference which I can see between these two projects is that in the working one, I am also Summary Task Owner, and that which is not working properly, have no summary task owner. Maybe something was wrong during MS Project synch?

 

Kind regards,

r.

2 REPLIES
Erik Cole
Acclaimed Contributor.

Re: Can't add task to work plan

What method are you using to add the task to a time sheet? Add Task? Suggested Items list?

 

Are the project's Cost & Effort settings adjusted to use Time Management?

 

Is the workplan set to Active status?

roxor
Honored Contributor.

Re: Can't add task to work plan

Hello Eric,

 

I have these Project Settings:

 

Cost and Effort

Track time at the: Summary tasks at hierarchy level: 5

Allow the following to report time on this project: All resources

After a task is complete, allow time to be logged: Do not allow

 

MS Project Integration

Integration mode for the project work: Control is shared

Transfer actuals information: Actual Efforts

 

Work Plan is set to Active.

 

I tried to search for tasks via 'Add Task' in the time sheet, no results. I am also using My Tasks portlet, where are these tasks listed but without possibility to click on the number where I fill values for actual effort - there is no number and it is blank. (You can see it on the printscreen in the row 2 and 3)

 

 

 

 

It is so weird.

 

Thanks a lot.

 

Kind regards,

r.