Calendar - only records full days off, not partial days/hours

Highlighted
kev marks
Super Contributor.

Calendar - only records full days off, not partial days/hours

We are trying to integrate a custom time off system that allows users to enter hours off, not only full days (i.e. 1/2 a day off), with PPM.
We are on PPM 7.1 SP4
It appears PPM only allows you to mark the full day off, not partial days/hours.
We are doing this integration b/c of resource management. We want the RM functionality to calculate the capacity correctly. But if a resource really only has 4 hours off but PPM reads this as 8 hours then the capacity will be off by 4 hours.
Does anybody have a workaround for this, or any suggestions?
Thanks
Kevin