Budget - only 5 digits to enter

Hello all
may be smb knows, is it possible to enlarge the field in the budget, so that i can enter more than 5 digits?
for example i need to enter 999999, but at this moment i can enter only 99999

rgs, Vasily Aksenov
5 REPLIES
Vadim Solenyi
Respected Contributor.
Solution

Re: Budget - only 5 digits to enter

It is the answer of company HP:

This is a limitation in PPM. There is already an enhancement request for this functionality.

ITG Product Enhancement - #185637

However, enhancments are not normally provided as part of a patch update, and they are reviewed as part of the planning for future ITG releases. As such,
I do not expect there to be a quick turnaround on an enhancement request.
Mert Kisman
Frequent Contributor.

Re: Budget - only 5 digits to enter

Hi Vasily,

Have you noticed that the numbers put in the budget lines are in 000s. When you enter 99999 it actually means 99 million which should be enough for a budget line in most cases.

I hope it helps somehow.
Vasily Aksenov
Acclaimed Contributor.

Re: Budget - only 5 digits to enter

hi
thanks, i know that it is in "000",
but i still need 6 digits.
Gary Rubinstein
Respected Contributor.

Re: Budget - only 5 digits to enter

I would recommend you add another budget line into the budget table and add the remaining value. For example, if you needed to add a budget line of 100,000 ('000) then you could enter this as 2 line of 50,000 ('000) each.
Vasily Aksenov
Acclaimed Contributor.

Re: Budget - only 5 digits to enter

Gary, thanks.
But it is workaround, and there are a lot of other workarounds too.
for example we can use Excel, or other products.
We opened ER.