Budget Start and End Dates Missing in HP PPM 8.02

Highlighted
James++
Super Contributor.

Budget Start and End Dates Missing in HP PPM 8.02

Hello Everyone,

In version 8.02 I am not able to find the Financial Summary Start and End Dates, as it was there in the HP PPM version 7.1 Budgets.

Does anyone have any idea on this.
1 REPLY
Jason Nichols K
Acclaimed Contributor.

Re: Budget Start and End Dates Missing in HP PPM 8.02

James,

Those fields were removed with version 8.0. The Planned Start and Planned Finish dates of the Proposal/Project now dictate the start and end periods of the Financial Summaries.

Jason