Baseline Functionality in PPM 7.1 sp5

Hi,

We have observed that, if we create baseline for a project will capture only the Planned figures of Workplan and not capturing Actuals and Planned values of Budget.

Is this the behaviour of the Baselines in PPM 7.1 SP5, or will it also capture the Actuals and Planned values of Budget?

Please could any help me out in knowing the baseline functionality.
3 REPLIES
Semenov Alexand
Esteemed Contributor

Re: Baseline Functionality in PPM 7.1 sp5

Hi Shravan.
Baselines capture the Actuals and Planned values of cost from work plan and use for report "Baseline comparision report" and for calculating SPI and CPI in EV Analysis
Amjad Damisi
Acclaimed Contributor

Re: Baseline Functionality in PPM 7.1 sp5

How about if you having multiple baselines, which baseline it will use?
Semenov Alexand
Esteemed Contributor

Re: Baseline Functionality in PPM 7.1 sp5

if you having multiple baselines then use only 1 active. Active can be only 1.