Project and Portfolio Management Practitioners Forum
cancel

Automatically Updating resource Calendar

Highlighted
sudhanshusk
Valued Contributor.

Automatically Updating resource Calendar

Hi All ,

 

We are looking to update Resource calendar from other leave management system like Oracle Applications etc .

However we do not see any interface table , Webservice method etc to update Resource Calendar in PPM from other application. Is there we can integrate these two system in such a way that Resource Calendar gets updated automatically .

 

Have any one done this before . Could you please help

 

 

Regards,
Sudhanshu

3 REPLIES
AlexSavencu
Acclaimed Contributor.

Re: Automatically Updating resource Calendar

Hi,

You can try to achieve this by updating the relevant tables in the database. I have never tried it before, but it is likely that I shall try it in the current project.

Cheers
Alex

--remember to kudos people who helped solve your problem
sudhanshusk
Valued Contributor.

Re: Automatically Updating resource Calendar

HP does not support a direct update on table , hence was looking for interface table ,webservice .

 

 

AlexSavencu
Acclaimed Contributor.

Re: Automatically Updating resource Calendar

Hi,

 

the correct statement is:

 

HP does not provide you support for any problems caused by manual table update.

 

cheers

alex


--remember to kudos people who helped solve your problem