Any option to turn off automatic calculation of EAC values?

Highlighted
happa
Super Contributor.

Any option to turn off automatic calculation of EAC values?

Hello,

 

Currently, we are in PPM 8.04 version.

 

Is there any option in PPM to turn off the automatic calculation of EAC values, so that the EAC values can be updated manually by the users.

 

Thanks in Advance for your reply.

 

Regards,

Sanjeeban.

1 REPLY
dirkf
Acclaimed Contributor.

Re: Any option to turn off automatic calculation of EAC values?

Hi Happa,

 

EAC - Estimate at Completion?

What exactly is it that you want to be able to manually edit?

 

You can set the project settings for some values, as there are

Scheduled Finish

Scheduled Duration

Estimated Finish date etc.

 

I'd need to have more information in respect what you do now, what is unsatisfactory about it and then I might be able to give my thoughts.

 

Best regards,

Dirk