Actuals in wokplan

We have users who will mark a task complete in the workplan  but they don't populate the actual completed date accurately.

 

 

By default  PPM or MSP will populate the actual completed date with the scheduled finish date.I know users can change the actual completion date of a task before marking it complete,but i want to find out if its possible to force users to reconfirm the actual date whenever they mark a task complete.

 

 

1 REPLY
Celil
Acclaimed Contributor.

Re: Actuals in wokplan

Hi patrick,

are these users project amangers or resources? As far as I know, when resources complete the task over timesheet, he can't change task completion date.
Celil