Nir Hadar
Occasional Contributor

Actual in graph

I want to present the actual progress in my project according to the actual effort submitted in timesheets by the workers but I can’t find any portlet the present this kind of information, is there any way to do it?
I need to present the effort invested in any of my project by a resource for a period (a month or so)
thanking you in advance
1 REPLY
Semenov Alexand
Esteemed Contributor

Re: Actual in graph

Hi Nir.
You need use the "Analize Assignment Load" portlet. This portlet alow you present planned and actual effort for project, org units and personal resources. But this portlect can't present load from TS to misclaneouse load. Only project and request with "Work items field" groups. This groups set in Request header type in Workbensh.
Good Luck.