Actual Time Summary Report

We are trying to run some of the canned time management reports in PPM and although the reports seem to run they fail to generate any data. Our users have time management licenses and are setup in resource pools. They report their time through the "My Tasks" and "My requests" portlets however we do not require them to use timesheets.
Do the hours reported need to be associated with actual timesheets in order to view actual hours at the resource an task level? Maybe this is our issue since our users dont use timesheets...
I have attached a screen print of the report we are referring to. Thank you for looking!
2 REPLIES
Surendra Poosar
Honored Contributor.

Re: Actual Time Summary Report

Hi,

The users must use the timesheets to view the data in the Actual Time Summary reports. The data displayed in the Actual Time Summary report is queried from the KTMG and some other tables. If you are not using the timesheets the report could not display any data.

 

Thanks

Tweed
Trusted Contributor.
Solution

Re: Actual Time Summary Report

Thank You very much for your response!