9.x staffing profile import

Highlighted
Erik Cole
Honored Contributor

9.x staffing profile import

Importing staffing profiles into 9.x using the XML tool, we're sometimes seeing strange results. In this case, we import a committed position and the forecast & allocation are correct. When I edit the header to pin the staffing profile to an Asset, upon save the page refreshes and now the forecast hours have shifted to the left four months so they are out of alignment with the allocation:

 

 

Has anyone seen this kind of behavior before?

//Add this to "OnDomLoad" event