7.5 SP6 running 7+ Hours

Highlighted
JAustin
Acclaimed Contributor

7.5 SP6 running 7+ Hours

We are in the middle of an upgrade to 7.5 for our production instance and the installation of SP6 has been running for 7 hours so far. This is the second server in our cluster. SP6 was applied to the first server in under 30 minutes. The SP6 installation on this server appears to be hung in the DeleteObsoleteOraDriver.sh phase. Is there any way to speed this process up? Should we kill it? Thanks
2 REPLIES
Jim Esler
Honored Contributor

Re: 7.5 SP6 running 7+ Hours

When we did our upgrades, we upgraded one instance and cloned it to rebuild the other instance. The database was already upgraded, so this worked fine and was quick.
JAustin
Acclaimed Contributor

Re: 7.5 SP6 running 7+ Hours

Thanks Jim. We ended up killing the process and restarted. Finished in the expected 30 minutes. Everything appears fine.